8 Defining the cycle time of the PLC project
8.2 Optimising the system
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
8.2 Optimising the system
How to optimise the system:
1. Use the menu command Online Login, or log in on the Lenze controller with <Alt>+<F8>.
With the log-in, the I/O device configuration is loaded into the controller.
2. Check the task processing times.
3. Optimising the cycle times:
If technologically required, the cycle times of the remaining tasks with lower priorities
can be decreased.
Condition: No task with a low priority must assign more than 60 percent of the
corresponding cycle time in its task utilisation.